The wall behind Midtown Beach runs 2,715 feet from Royal Palm Way south to Gulfstream Road. It has been there for close to a century. It sits under the coconut palms of the linear park, the Worth Avenue Clock Tower and the eastern parking spaces along South Ocean Boulevard. Town officials say failure is not imminent. Jake Hurley of the Public Works Department told the Town Council that "we have multiple engineering reports that it is near the end of its useful life," the Palm Beach Civic Association reported.
The replacement is now close. It is expected to take about 18 months and could close Midtown Beach for all of that time. The start date is set by the sea turtle nesting season, not by the social season. In the same window, the island's other lifeguarded public beach, Phipps Ocean Park, is due to reopen after a two-year rebuild. That pushes Palm Beach's public beach use toward the south end.
Why the Work Starts When the Beach Is Busiest
The winter start follows the nesting calendar. Turtle nesting runs from March 1 to Halloween each year. At the October 13 Town Council meeting, Hurley said staff want to start as soon as possible this winter so construction stays within one nesting season, the Palm Beach Daily News reported.
Earlier beach work makes this possible. Midtown Beach got a major infusion of sand this spring. Hurley said that sand will be used to build seaward barriers so turtles do not nest inside the construction site. The same sand that widened the beach for this season is what lets the town close it.
The schedule has moved more than once. In September, officials expected a December start, and the Civic Association reported that a full closure would leave Midtown Beach closed from December until spring 2028. A Daily News photo caption now puts the start "sometime during the early months of 2027." If work starts this winter, the paper says, it is forecast to run until spring 2028. Both dates are planning estimates. The firm schedule should arrive with the contractor's guaranteed maximum price, which Hurley said could come as early as November along with drawings, visuals and a detailed timeline.
Why a Full Closure Is the Likely Outcome
Whether the beach closes completely or partly is still open. In September, Council member Lew Crampton asked for more discussion before the council decides. The cost case points toward a full closure. The design-builder, Murray Logan Construction of West Palm Beach, plans a dune that leaves little room for beach access during the work. Asked about keeping part of the sand open, Hurley said:
"But, very likely, it would be extended duration of the project and extended cost."
He said that in remarks reported by the Palm Beach Civic Association. In October, the Palm Beach Daily News reported a stronger estimate from staff: building in stages could make costs skyrocket and double the length of the project. Crews would need a more complex mobilization, and buying materials later in the timeline could raise costs if the economy weakens. A staged project would also run into a second nesting season, which is the outcome the winter start is meant to avoid.
The seawall is expected to cost $20 million or more. That figure includes $1.5 million the council set aside in July for design and planning. Mayor Danielle Moore said the town has been discussing the project for years and it is time to get it done.
From South Ocean Boulevard, people will see barriers along the eastern parking spaces, covered in screening printed with an ocean scene. Hurley said two-way traffic on the boulevard will stay open throughout.
The Promenade Comes Back Larger
There is a second project behind the barriers. The town has budgeted about $4 million to redo the Midtown Beach Linear Park, the strip between South Ocean Boulevard and the beach. Work on it is planned to begin toward the end of the seawall construction. The proposed design, as reported by the Civic Association, includes:
- 15,000 square feet of added open space, a 48 percent increase over the current park
- One wider sidewalk in place of today's two
- New benches, more landscaping and new beach stairs at Royal Palm Way
- A terrace at the Worth Avenue Clock Tower, so people can walk through the tower to an ocean view
- Traffic islands on South Ocean Boulevard and new pedestrian crossings at Brazilian Avenue and Royal Palm Way
The plans also include "pocket parks" east of each intersection along that stretch. At the council's August 11 meeting, some members objected to the proposed sidewalk layout between Royal Palm Way and Chilean Avenue.
The 42 coconut palms are the detail regulars will watch most closely. Town Engineer Patricia Srayer said the town intends to keep as many as possible. Palms will stay in place where they can, or be relocated and replanted in the park, and some will likely need to be replaced. The redesign, including the palm plan, was scheduled for the Architectural Commission on October 28.
The Public Beach Shifts South
Midtown is one of only two public beaches in the town with lifeguards. Crampton, who lives on the South End, expects displaced beachgoers to head to the beaches east of Sunrise Avenue and to Phipps Ocean Park. "Those folks are going to go south, and you are going to have a potential overload there," he said, according to the Palm Beach Civic Association.
Phipps will look different when it reopens. The Preservation Foundation of Palm Beach, working with the town, began a major redesign in May 2025. Its estimate keeps the park closed to the public until November 2026. The tennis center and its parking were set to reopen earlier, on November 1, 2025. The $30 million Extraordinary Spaces @Phipps Ocean Park campaign aims to complete the Phipps family's 1948 gift, a public park that runs from the Atlantic to the Intracoastal Waterway with 1,200 feet of oceanfront.
The Little Red Schoolhouse is also moving. It is Southeast Florida's first schoolhouse and the oldest landmark in Palm Beach, and it is being relocated to higher ground near the dune. Next to it is the new Coastal Restoration Center, a nursery that grows native plants for dunes in the park and across town. So the park reopening this winter includes a working nursery for the kind of dune Murray Logan plans to build at Midtown.
Farther south, Palm Beach County runs R.G. Kreusler Memorial Park at 2882 S. Ocean Boulevard.
| Beach | Who runs it | Status this winter | What's there |
|---|---|---|---|
| Midtown Municipal Beach | Town of Palm Beach | Expected to close, partly or fully, for about 18 months | Seawall replacement, then a linear park redesign |
| Phipps Ocean Park | Town, with the Preservation Foundation | Reopening estimated for November 2026 | 1,200 feet of oceanfront, Little Red Schoolhouse, Coastal Restoration Center |
| R.G. Kreusler Memorial Park | Palm Beach County | Open | 450 feet of guarded frontage, fee parking, restrooms, outdoor showers |
Kreusler is guarded by County Ocean Rescue, and the county posts daily conditions for its South District beaches on its beach conditions page. Phipps has not yet published details on lifeguards and amenities for its reopening, so check with the town before planning a first swim there.
Dates to Watch
- October 28. The Architectural Commission's scheduled review of the linear park redesign and palm plan.
- October 29. The town's public presentation and open house on the project's goals and effects on the community, set for 2 to 3 p.m. in Town Council Chambers, 360 S. County Road. Details are on the town's calendar listing.
- November. The earliest Hurley expects Murray Logan's guaranteed maximum price and detailed schedule. It is also the Preservation Foundation's estimated reopening month for Phipps Ocean Park.
- December to early 2027. The range of start dates reported so far for seawall construction.
- March 1. The start of turtle nesting season. By then the seaward barriers need to be in place.
- Spring 2028. The forecast finish if construction starts this winter. Work on the new linear park follows.
For owners whose mornings begin on South Ocean Boulevard, the seawall schedule will shape how they use the island for the next two seasons. Margit Brandt follows each step of the Midtown project, from the guaranteed maximum price to the Architectural Commission's decision on the palms, and can explain how the construction period and the redesigned promenade relate to a property near Worth Avenue or the South End. Request a private consultation.