The Last Power Poles on Palm Beach Are Coming Down. Here's Where the Crews Are This Season.

November 12, 2026

During the week of Nov. 9, Bahama Lane between North Lake Way and North Ocean was closed to all but local traffic for two days while crews took down poles and wire. Then the crews moved onto North Ocean to do the same. The town's schedule calls this "Overhead Wreck Out." In practice, it is the last time those poles stand on those blocks.

Palm Beach voters approved funding for town-wide undergrounding in 2016, and construction began in 2017. For most of the years since, the work happened mostly below ground and looked about the same from one street to the next. That has changed this season. The three phases with crews still working are each at a different step of the same sequence, and the step tells you how close your street is to being done.

Six Steps, and the North End Is Near the End

The town's Undergrounding Program guide says every street goes through the same sequence:

  1. Prepare. Crews survey the utilities, obtain easements and identify where each property will connect.
  2. Drill. Horizontal directional drilling creates underground pathways with less surface disruption.
  3. Install. Conduit and the rest of the underground equipment go in.
  4. Connect. Homes and businesses are switched from overhead lines to underground service.
  5. Remove. Overhead wires, transformers and utility poles come down.
  6. Restore. Roads, sidewalks, landscaping and other affected areas are repaired.

Steps two through four are easy to miss. Drilling causes lane closures, but the conduit is out of sight once it is in place, and connections often happen in back yards. Steps five and six are the ones you can see. On the North End, this fall is when those steps arrived. The guide counts 9,598 electric meters already moved to the new network.

Three Phases, Three Different Steps

The town's October 2026 Town Tides newsletter names Phases 7S and 8 as the program's final phases. It reports Phase 7N complete and due for landscaping this fall, and says homes in 7S are now being connected. In 7N, the remaining work is taking down the old overhead lines. The weekly schedule for Nov. 9 shows each phase at its own step.

Phase Boundaries Step Where crews worked the week of Nov. 9
7N Palm Beach Country Club north to List Road Remove Poles and wire on Bahama Lane, then North Ocean
7S Atlantic Avenue north to Via Los Incas and Sanford Avenue Connect and Restore Feeder wire on Bradley Place and North Lake Way between Wells Road and Sanford; sidewalk restoration on Atlantic Avenue, Dunbar and Wells Road
8 Royal Poinciana Way north to Everglade Avenue Drill and Install Drilling on North County Road from Seminole Avenue to Royal Poinciana, on Everglade and on Seminole; tie-ins on North County from Atlantic to Sunrise

Each step brings a different kind of disruption, so each part of the island will have a different season. With its construction done, Phase 7N is down to the Remove step, which means short closures and work that finishes one block at a time. Phase 7S still has wire to pull, connections to make and sidewalks to repair. The schedule says lane closures on Bradley Place and North Lake Way will keep traffic moving, and the sidewalk crews on the east-west streets will close lanes temporarily as they move. Phase 8 is still at the start of the sequence. Its poles will not come down until its own drilling, installation and connection work is finished.

Wells Road, Where the Finished Work Shows First

Wells Road is where the program's last step meets the town's other projects, and it is the first place the North End will look finished.

The 7S sidewalk restoration reached Wells Road during the week of Nov. 9. A few blocks away, North County Road between Wells Road and Tangier Avenue reopened in both directions on Oct. 14 after drainage work, the Palm Beach Daily News reported. The town's October newsletter says the new park at Wells Road and North County will open in December, together with a new tree canopy on North County.

The park started as a traffic project. At its April 9, 2025, development review meeting, the Town Council unanimously approved a small pocket park along with changes to the intersection of Wells Road, Crescent Drive and North County Road. The Daily News described that intersection as hazardous. Earlier that year, the council approved conceptual plans for a park near the redesigned North Fire Station and accepted a private donation to build it, the paper reported. A June 2026 council agenda included a resolution to accept a $265,000 donation for building Wells Park.

The streets have been resurfaced too. The town's contractor finished paving more than 7 miles of road in Midtown this summer, plus 3 miles between Bahama Lane and Laurian Lane. Taken together, the poles coming down, the new pavement, the restored sidewalks, the reopened North County Road and the park make the North End the first part of the island where most of the work is finished.

Phase 8 Moves Into the Island's North Core

The final phase covers the blocks between Royal Poinciana Way and Everglade Avenue. During the week of Nov. 9, crews drilled conduit under North County Road from Seminole Avenue to Royal Poinciana and under Everglade between Bradley Place and North County Road. They also ran service lines to individual addresses on Seminole. The schedule says lanes will close and traffic will keep moving.

A separate project is working in the same part of the island. The Cocoanut Row Watermain project closed the southbound lane of Cocoanut Row between Royal Poinciana Way and Pendleton Avenue for restoration work that week, with flaggers directing traffic.

Some of the slowdown has had nothing to do with Palm Beach. Florida Power & Light crews assigned to the project were sent elsewhere twice in 2026 to help restore power after storms, Town Engineer Patricia Strayer told the Palm Beach Daily News. As of July 2025, the same paper reported that the $128 million program was on track to finish in 2027.

The Calendar Sets the Pace

Once the season starts, the main limit on the crews is how many days they are allowed to work. The town's construction working-hours schedule, revised July 16, 2026, sets winter hours from Nov. 1 through April 30.

With Thanksgiving week and the stretch from Christmas Eve through New Year's Day removed, crews lose a large share of their working days between now and mid-January.

Weekly closures by phase are posted on undergrounding.info, and the town's October newsletter and program guide show the overall picture. If you own a North End estate that is coming out of construction, or you are thinking about buying a house on a Phase 8 street, Margit Brandt Palm Beach can tell you where that property sits in the sequence and what the work means for your timeline. Request a private consultation.